User’s Manual
102
26.
We now need to add a super elevation at the end of
the curve on the left side of the road to change the
slope back to -2%.
27.
With
<End>
selected in the
L
eft column, tap the
button again.
28.
From the Add Left Super Elevation
screen we will
start the transition out of the super elevation, 200
feet from the beginning of the road so enter
2+00
in
the
Start Station
field.
29.
The super elevation will return to the original slope
after 25 feet so enter
2+25
in the field.
30.
The start slope must be the same as the slope of the
road where it leads into the super elevation, so leave
the
Slope 1
field set to 8.
31.
We want the ending slope to be -2% so in the
Slope 2
field, enter
-2
. Leave the parabolic transition fields set to 0.
32.
Be sure the
Hinge on
field is toggled to and
then tap OK
to continue. This will complete the super elevation
entries for the left side of the road.